Plan Vivo is the carbon standard built for projects where many small farmers and communities plant and look after the trees. Its rules are different from Verra's in ways that matter early: who may take part, how the money is shared, how big the buffer is and when certificates can be issued. This post explains the PV Climate standard for tree-planting and agroforestry projects, using the current documents, and where it overlaps with the land questions a feasibility screening answers.
What PV Climate is
The Plan Vivo Foundation is a charity registered in Scotland. Its carbon standard is called PV Climate, and Plan Vivo describes it as the longest-standing carbon standard in the voluntary market, with roots in the 1990s. It certifies “community and smallholder-led nature-based projects”: restoration (tree planting, assisted natural regeneration), agroforestry, protection and improved management. It does not certify energy projects such as clean cookstoves.
The rules sit in three documents: the Project Requirements (v5.7, April 2026), the Procedures Manual (v3.9) and the validation and verification requirements. The carbon is quantified with a Plan Vivo methodology, such as PM001 for agriculture and forestry or PM002 for small-scale agroforestry, plus a project-specific technical specification.
- Benefit shareAt least 60% to communities
- Risk buffer20%, fixed
- Crediting period10 to 50 years
- VerificationAt least every 5 years
Who can take part
Plan Vivo projects are run by a project coordinator: a legally established organisation that takes overall responsibility for the project for its whole life, usually an NGO, cooperative or local company. The people who plant and manage the trees are the project participants, and the requirements are specific about who they are:
- They live in the project region and use the land for subsistence or small-scale production (Project Requirements 2.3.1).
- They are not structurally dependent on year-round hired labour (2.3.2).
- Participants who do not meet those tests may take part only if their land stays under 30% of the total project area at all times (2.3.3).
- Participants need statutory or customary rights that let them carry out the land management and benefit from the sale of certificates (1.2.1), and the project must not cause forced physical or economic displacement (1.2.3).
Free, prior and informed consent is a requirement, not a guideline: the rights holders take a collective decision to grant or withhold consent, before the activity takes place, and consent is re-confirmed periodically (2.6). A single large landowner planting a commercial block is not the case Plan Vivo was designed for; a programme with hundreds of farm plots is.
The 60% benefit rule
The rule Plan Vivo is best known for is in section 3.16.2 of the Project Requirements: at least 60% of income from the sale of Plan Vivo Certificates, after host-country charges and taxes, must directly benefit the project participants and other local stakeholders. The share may be lower for a single issuance as long as the total over the crediting period reaches 60%.
The other side of that rule matters for planning. If coordination, management, monitoring, reporting and verification cost more than 40% of the income, the guidance says the coordinator has to find other funding. A business plan for a Plan Vivo project therefore has to show that the coordinator can run the programme on 40% of certificate income or less, or bring in grant money. Small volumes make that hard.
The project cycle
Project Idea Note (PIN)
A short description reviewed by Plan Vivo. If it is approved, the project is listed in the pipeline. Plan Vivo indicates about six weeks for the review.Project Design Document (PDD)
The full design, with the technical specification that quantifies the carbon benefit, reviewed by Plan Vivo and its Technical Review Panel (indicated at about eight weeks). See the project design document for ARR for what such a document covers.Validation and certification
An accredited validation and verification body (VVB) audits the design. Microscale projects, which expect no more than 10,000 certificates a year, can choose an internal route with independent experts instead. After validation the project registers and becomes certified.Annual reports and verification
Every certified project submits an annual report, and must be verified at least every five years, with a final verification at the end of the crediting period.
A project start date can be up to five years before validation, with a strong additionality argument. A project cannot be registered under PV Climate while it is actively registered under another carbon crediting program (3.13.5).
Future certificates and a fixed buffer
Plan Vivo issues three kinds of certificate, which is the biggest practical difference from Verra for a tree-planting project:
| Certificate | When it is issued | What it means |
|---|---|---|
| Future (fPVC) | Ex-ante, for expected removals such as tree planting | Up to 90% of the expected carbon benefit; lets a project raise money up front; cannot be retired |
| Reported (rPVC) | Ex-post, reported but not yet verified | Cannot be retired until verified |
| Verified (vPVC) | Ex-post, after a verification | The only type that can be retired |
The 10% that cannot be issued ex-ante is held in an achievement reserve. On top of that, 20% of every issuance goes to a risk buffer (3.11.3 and 3.11.4). The figure is fixed for all projects. Under Verra, the buffer is set project by project with the AFOLU Non-Permanence Risk Tool; our registry data puts the median for registered ARR projects at 15%, as explained in the non-permanence buffer. Plan Vivo also asks projects to identify risks to the carbon over at least 50 years.
One caution for buyers and funders. Plan Vivo states that future and reported certificates do not meet the ICVCM Core Carbon Principles or CORSIA criteria, and that a CCP label for verified certificates depends on a CCP-approved Plan Vivo methodology with at least 40 years of monitoring. The ICVCM approved PV Climate as a CCP-Eligible program on 4 August 2026; for the methodologies, check the ICVCM assessment status page before relying on a label.
Land rules for tree planting
Several PV Climate rules are close to the land tests in Verra's VM0047, so the same desktop evidence answers both:
- No conversion of natural ecosystems. “Natural Ecosystems must not be converted to generate Carbon Benefits” (3.9.13). The guidance gives clearing natural forest, planting trees on native grasslands and draining wetlands as examples, and asks projects to show no conversion in the 10 years before the intervention (up to 15 where data is lacking). Grassland is a real trap; see planting trees in grasslands and savannas.
- Native species. Trees must be native to the project region unless they bring clear livelihood or ecosystem benefits (3.9.10). Since v5.5, single-species plantings over one hectare are prohibited unless the PDD shows, among other things, native or naturalised species and a time-bound plan to move to a mixed system.
- The forest history. The PM002 agroforestry methodology also excludes clearance of woody vegetation in the previous 10 years and planting on wetlands. Our explainer on the 10-year rule shows how that is checked from satellite data.
On the smallholder sites we have screened, the forest history decided the most. A montane agroforestry site in Kenya of about 420 ha was 93% eligible following VM0047; an agroforestry landscape in western Uganda was 16% eligible, because most of the boundary already counted as forest. Plan Vivo's own tests are not identical, but a boundary that is mostly existing tree cover is a weak start under any standard.
Fees
Plan Vivo publishes its fees in US dollars (plus VAT for UK organisations). For a project that issues certificates, the schedule lists:
| Item | Fee | Note |
|---|---|---|
| PIN review | $1,000 | All projects |
| PDD review | $1,500 or $3,000 | Depends on project scale (macroscale or microscale) |
| Validation and verification coordination | $1,000 or $2,000 | Plan Vivo review and registration; the auditor is paid separately |
| Issuance | $0.40 per certificate | $0.35 per certificate above 50,000 a year |
The fees exclude the cost of the VVB or independent expert, which Plan Vivo says is project-specific and does not publish. The larger costs are the coordinator's: years of community engagement, nurseries, plot monitoring and annual reporting. For the wider picture, see what it costs to develop an ARR project.
When Plan Vivo fits, and when it does not
Plan Vivo fits programmes where the trees are planted on many small farms or community land, where the benefit-sharing model is part of the point, and where future certificates can bridge the long gap before the first verified credits. It fits less well where one owner holds the land, where the coordinator's costs would exceed 40% of income, or where buyers specifically want Verra units or units already carrying the CCP label. The trade-offs between the three main standards are set out in choosing a carbon standard.
Feasibility.Earth screens tree-planting projects following Verra's VM0047, not the PV Climate rules. Much of what a reforestation feasibility study checks (forest history, recent clearing, water and wetland, slopes, growth rates and leakage) is the same evidence a Plan Vivo technical specification will need.
Frequently asked questions
Plan Vivo is a carbon standard run by the Plan Vivo Foundation, a charity based in Edinburgh. Its carbon standard, PV Climate, certifies nature-based projects led by communities and smallholders, including tree planting, agroforestry, protection and improved land management. Certified projects issue Plan Vivo Certificates (PVCs).
Under the PV Climate Project Requirements v5.7, at least 60% of the income from selling Plan Vivo Certificates, after host-country charges and taxes, must directly benefit the project participants and other local stakeholders. The share can be lower for a single issuance, as long as the total over the crediting period reaches 60%.
Plan Vivo has a future certificate, the fPVC, which can be issued ex-ante for removals such as tree planting, for at most 90% of the expected carbon benefit. Only verified certificates (vPVCs), issued after a verification, can be retired against a claim, and Plan Vivo states that fPVCs do not meet the ICVCM Core Carbon Principles or CORSIA criteria.
Yes, at program level. On 4 August 2026 the Integrity Council for the Voluntary Carbon Market announced Plan Vivo (PV Climate) as a CCP-Eligible program, for projects registered under Project Requirements v5.7 or later and audited by accredited validation and verification bodies. A CCP label also needs a CCP-Approved methodology; check the ICVCM assessment status page for the current status of the Plan Vivo methodologies.
Not on native grassland. PV Climate requires that natural ecosystems are not converted to generate carbon benefits, and its guidance gives planting trees on native grasslands as an example of conversion. Projects also have to show there was no conversion in the 10 years before the intervention starts.
Sources
- Plan Vivo: PV Climate Project Requirements, v5.7 (30 April 2026)
- Plan Vivo: PV Climate Procedures Manual, v3.9
- Plan Vivo: PV Climate Costs & Fees
- Plan Vivo: Certify a carbon project (PV Climate)
- ICVCM: CCP-Eligible program decisions for BioCarbon Standard, Cercarbono and Plan Vivo (4 August 2026)
- Verra: VM0047 Afforestation, Reforestation and Revegetation, v1.1