The ARR carbon project timeline: from idea to first credits

A tree-planting carbon project runs on two clocks. One is set by the rules: Verra's deadlines for listing, validation and verification. The other is set by the trees: credits follow growth, and young trees grow slowly. This post walks through the stages in order, the deadlines that apply to each, and the date that matters most for your finance plan.

Feasibility.Earth team, Green Earth Group · Updated

Everything counts from the project start date

Most deadlines in the Verra VCS Program are counted from the project start date: for a tree-planting project, broadly the date the activities that remove carbon begin, such as site preparation or planting. It is not the date you start talking to landowners or commission a study. VM0047 makes one point explicitly: setting up measurement plots does not make the start date.

The start date is a design choice with consequences. It fixes which version of the rules applies, it starts the validation deadline, and it sets the window for measuring the starting carbon stock. This post quotes the VCS Standard v4.7. Verra issued v5.0 in December 2025 and keeps v4.7 active until 1 July 2027 for projects that may still apply it, so check the program details page for the version that applies to yours.

  • Pipeline listingWithin 3 years of start
  • Validation (ARR)Within 8 years of start
  • VerificationAt least every 5 years

The stages of an ARR project, in order

The order below is the usual one. Some stages overlap, and planting can begin before validation, but each one depends on the decisions made before it.

  1. Feasibility

    Is the land eligible, how much could it remove, and what is left after the deductions? A desktop carbon feasibility study answers this in days, not months: 2–3 business days for an Eligibility Check and 5 for a Full Feasibility Study, from a complete intake.
  2. Land rights, consultation and consent

    Agreements with landowners and communities, free, prior and informed consent where it applies, and a benefit-sharing plan. This is usually the slowest stage to do well, and it cannot be done from a desk.
  3. Design and the project description

    Field inventories, species and planting plans, the baseline, additionality, leakage, the non-permanence risk analysis and the monitoring plan, all written into the project description. See the project design document for ARR.
  4. Pipeline listing and public comment

    The project is listed on the Verra pipeline, first as under development or directly as under validation. Listing as under validation opens a 30-day public comment period.
  5. Validation and registration

    An accredited validation and verification body (VVB) audits the design. Once it concludes, the proponent may request registration, which Verra reviews.
  6. Planting and monitoring

    Nurseries, planting, protection and replanting, and plot measurements under the monitoring plan.
  7. Verification and issuance

    A VVB verifies the monitoring report, Verra reviews the verification request, and only then can the proponent request issuance of credits.

The deadlines that set the clock

The VCS Standard and the Registration and Issuance Process set hard limits. Missing them can mean a project cannot register, or that its buffer credits are frozen.

Verra deadlines that apply to a tree-planting project
StageRuleWhere it is set
Pipeline listingAFOLU projects must start the pipeline listing process within three years of the project start dateVCS Standard v4.7, 3.8.2
Verra review of the listingIssues raised by Verra must be answered within 90 days, or the project is inactivatedRegistration and Issuance Process v5.0, 3.1.13
Public commentEvery project has a 30-day public comment period, which starts when it is listed as under validation; the VVB cannot finish validation before it endsVCS Standard v4.7, 3.18.9 and 3.18.13
ValidationARR projects of any size must complete validation within eight years of the project start date (non-AFOLU projects: two years)VCS Standard v4.7, 3.8.3 and 3.8.1
Crediting periodThe initial crediting period is at least 20 and at most 100 years; total not to exceed 100 yearsVCS Standard v4.7, 3.9.3
VerificationA verification approval request is due within five years of registration or the last approved verificationRegistration and Issuance Process v5.0, 4.1.2
PermanenceThe permanence of carbon stocks must be monitored for at least 40 yearsVCS Standard v4.7, 3.2.24

The eight-year validation window is generous compared with other project types. It reflects the fact that tree planting often starts before the paperwork is finished. But it is a ceiling, not a plan: until validation and registration, the project cannot request verification, so it cannot issue credits.

The trees set the pace of the first credits

A verified carbon unit represents a removal that has already happened. In the first years after planting, trees are small and removals are low, so the first verification is usually timed for when enough carbon has built up to justify the cost of the audit and Verra's review fee.

How long that takes depends mostly on the climate zone. The IPCC 2019 Refinement's Tier 1 growth rates for young plantings in Africa (above-ground only, first 20 years) run from about 0.8 tCO2e per hectare per year in tropical shrublands to about 13.1 in tropical rainforest. That is a more than fifteen-fold difference, and the screenings we have run sit across that whole range. A dryland project may need several more years of growth than a humid one before a verification pays for itself. See carbon sequestration per hectare for the rates by zone.

Under VM0047, the measurements themselves have a timetable. Where site preparation clears or reduces existing woody vegetation, the starting carbon stock must be measured in plots before site preparation and no more than two years before the start date. Where preparation does not significantly reduce the existing stock, for example pit planting without clearing, plots can be set up within two years after the start date. The plot measurements in the monitoring plan are then repeated every five years or more often. More on how the method works in VM0047 explained.

After the first issuance

A tree-planting project is a decades-long commitment. After the first issuance, three timing rules shape the years that follow:

  • Verify at least every five years. A project that does not submit a verification approval request within five years of its last approval is marked late to verify, and all its buffer credits are put on hold until it does.
  • Buffer releases come slowly. The first release of buffer credits can come no sooner than five years after the first verification report was approved for issuance, and later releases at most once every five years. See the non-permanence buffer.
  • Losses must be reported. A fire or other loss event must be reported to Verra within 30 days of its discovery, and the project cannot issue more credits until the loss event report is in.

How to plan the timeline

Three practical points follow from the rules and the biology:

  1. Decide feasibility before the start date. Once activities begin, the deadlines run. A site that turns out to be ineligible after planting has used up time and money. A screening takes days; finding out during validation can take years.
  2. Put the baseline measurement in the plan. If site preparation will clear existing vegetation, the starting-stock plots must be measured before it. Build that into the planting calendar.
  3. Plan cash around the first verification. The costs of design, validation and planting come years before the first credits. The carbon project development guide covers who does what, and what it costs is in the cost of developing an ARR project.

Frequently asked questions

There is no single answer, because most of the time goes into consultation, design and tree growth, which depend on the site. What is fixed are the deadlines. Under the VCS Standard v4.7, an AFOLU project must start pipeline listing within three years of its start date, and an ARR project must complete validation within eight years of it. After registration, the project must request verification approval at least every five years.

Sources