Guide · Project development
Carbon project development: the path from idea to issued credits
Developing a tree-planting carbon project takes years and several independent parties. This guide sets out the stages in order, who does what, what each stage costs you in time and risk, and why the feasibility study comes first.
- 01Pre-feasibility: eligibility
- 02Feasibility study
- 03Land, rights and consent
- 04Field data and PDD
- 05Validation and registration
- 06Implementation
- 07Monitoring and issuance
- 08Sales and reporting
The stages of a carbon project
The order below is for a tree-planting (ARR) project under the Verra VCS Program and the methodology VM0047. Other standards use different names but a similar sequence.
Idea and pre-feasibility
Is the activity eligible, and is enough land eligible? An eligibility check answers this from satellite data in days.
Feasibility study
Species, carbon removals, the gross-to-net deductions, risks and next steps. The go or no-go point for spending real money. See the feasibility study guide.
Land, rights and consent
Secure the land and carbon rights, agree benefit sharing, and obtain free, prior and informed consent from the communities involved. Check host-country rules on carbon projects.
Field data and project design
Field inventories, a monitoring plan and the Project Design Document (PDD), which applies the methodology to your site.
Validation and registration
An accredited validation and verification body (VVB) audits the PDD against the standard. The project is then registered and listed on the registry.
Implementation
Nurseries, planting, protection and replanting where trees die. This is where most of the money goes.
Monitoring, verification and issuance
Each monitoring period the project measures its removals, a VVB verifies them, and the registry issues credits, minus the buffer contribution.
Sales and reporting
Credits are sold, forward or after issuance, and the project keeps reporting for its whole crediting period.
Who does what
| Role | When | |
|---|---|---|
| Landowner or community | Holds the land; agrees to the project and the benefit sharing | Throughout |
| Project developer | Runs feasibility, design, registration, implementation and monitoring | Throughout |
| Validation and verification body (VVB) | Independent audit of the design and of each monitoring report | Validation; each verification |
| Standard and registry | Sets the rules, registers the project, issues and tracks credits | Registration; issuance |
| Buyer or investor | Funds the project or buys the credits | Before or after issuance |
Cost and time
Costs vary too much by country, size and standard for an honest single number. The main cost items are the feasibility work, field inventories, writing the PDD, validation and verification fees, registry fees, and, by far the largest for tree planting, establishing and maintaining the trees. Ask any provider to quote each item separately; what to compare when pricing a feasibility study lists the questions to ask.
On time: tree-planting projects are slow to pay back. Credits come only after removals have happened and been verified, and young trees remove little in their first years. Plan your finance around the first verification, not the planting date. The Verra deadlines for each stage are in the ARR project timeline, and the published fees and per-hectare planting costs in what it costs to develop an ARR project.
Why the feasibility study comes first
Each stage costs more than the one before it, and the most common reasons projects fail can be seen at the start: land that does not qualify, growth too slow for the climate, leakage that eats the net, or an area too small for the fixed costs. Finding that out for $500 to $7,500 is cheaper than finding it during validation. More on this in why carbon projects fail feasibility.
Where Feasibility.Earth fits
Feasibility.Earth covers the first two stages for tree-planting projects under VM0047: the $500 Eligibility Check and the $7,500 Full Feasibility Study. Both are desktop screenings; neither is a validation or a credit claim.
For projects that pass a full study, Green Earth Group offers project development support: PDD, certification and registration, implementation, monitoring and credit sales. For some qualifying projects it considers co-investment. That is decided case by case after the study, never before. See how this compares with a consultancy.
Frequently asked questions
Start by testing whether the land and the activity can produce credits at all: a pre-feasibility or eligibility screen, then a feasibility study. Only then secure land and carbon rights, consult the communities involved, and write the Project Design Document for validation. Starting with design or marketing before feasibility is the most common expensive mistake.
The organisation that takes a project from idea to issued credits: it runs feasibility, writes the Project Design Document, manages validation and registration, organises implementation and monitoring, and usually markets the credits. Landowners can develop a project themselves or work with a developer under a contract that sets out costs and the split of revenue.
Costs depend heavily on project size, country and standard. The main items are feasibility, field inventories, the Project Design Document, validation and verification by an accredited body, registry fees, and the cost of planting and maintaining the trees. Our part is fixed: $500 for an eligibility check and $7,500 for a full feasibility study. Everything after that is quoted per project.
Years rather than months. Credits are issued only after removals have happened and been verified, and young trees grow slowly. Design, validation and registration also take time before the first monitoring period starts.
Feasibility.Earth is the screening service of Green Earth Group. For projects that pass a full feasibility study, Green Earth Group offers project development support and, for some qualifying projects, considers co-investment. That is a separate engagement, decided case by case.